Maria has scheduled the ceiling and wall insulation inspections (2 different inspections!). Around 10.00 am our inspector Kent comes by to check if the insulation installation is per code. This time we pass without any change requests. He signs both inspections and off he drives. These inspections are our favorites.
|
|
The rolldowns came in parts, i.e. Juergen has to assemble the tracks, the box, the shaft, the motor and the shield.
Juergen assembling the box and the tracks: |
The next step is to measure the exact length and width |
|
|
|
|
Before Juergen closes his "workshop" today he gives the soffits a first try.
Our construction plans specify that we have to install vented aluminum soffits. The fascia will be installed later on along the roof edge:
Exempt from the construction drawing:
And in case we decide later on to install little recessed spots in front of the patio doors Juergen prepares
cables for them:
Measuring the cable: |
Preparing the cables: |
We will connect the cables only if we install some lights.
If you rollover with the mouse (NOT click)
you get information about the work done on that date.
If you click on the date the page for that day opens!
February |
March |
April |
May |
|
July |
August |
|